Project Overview

We were engaged to perform a targeted demolition of the lower kitchen cabinet in a typical HDB flat. The homeowner required the removal of the base cabinet that runs beneath the sink to accommodate a new layout and services upgrade. Our team executed a precise dismantling of the built‑in cabinetry, carefully extracting the cabinet carcass, toe‑kick, and associated panels while preserving the surrounding wall tiling, benchtop, and floor finishes. All debris was collected and disposed of in accordance with HDB regulations, leaving a clean, ready‑to‑renovate space for the next phase of the interior works.

Technical Challenges

ChallengeHow We Addressed It
Limited Working Clearance – The cabinet sits under the sink with plumbing and a valve stub directly behind it, leaving very little room for tools and personnel.We employed compact hand tools and low‑profile pry bars, allowing us to detach doors, panels, and the toe‑kick without damaging the adjacent pipework.
Preservation of Adjacent Finishes – The surrounding tiled floor and wall finishes had to remain intact to avoid costly re‑tiling.We used protective sheeting only on the immediate work zone and applied gentle tapping techniques to lift tiles where necessary, ensuring the surrounding tiles stayed undisturbed.
Dust and Debris Containment in a High‑Rise Environment – HDB units are stacked vertically, making dust migration a concern for neighboring households.A combination of localized vacuum extraction and frequent sweep‑and‑wipe cycles kept dust levels low. We also sealed the cabinet opening with temporary barriers during peak demolition moments.
Safe Handling of Built‑In Carpentry – The cabinet structure is integrated with the countertop and wall supports, requiring careful dismantling to avoid structural compromise.Our carpentry specialists identified the load‑bearing points, removed the cabinet in sections (door, side panels, base) and used temporary support props where needed before complete extraction.

Project Considerations

  • Resident Comfort & Minimal Disruption – Working hours were coordinated with the homeowner to avoid peak cooking times, and we maintained a tidy site throughout the day.
  • Safety Protocols – All team members wore PPE, and the work area was clearly cordoned off to prevent accidental entry. Electrical tools were checked for compliance with HDB safety standards.
  • Communication – Progress updates, photos of the cleared area, and any unexpected findings (e.g., the pipe stub) were shared instantly via WhatsApp, ensuring the homeowner and interior designer stayed fully informed.
  • Disposal Compliance – Dismantled cabinet wood, broken tiles, and dust were bagged and removed in sealed containers, adhering to HDB waste‑management guidelines.

Results

The bottom kitchen cabinet was fully removed, exposing a clean, level sub‑floor and service cavity ready for the new design. All removed materials were responsibly disposed of, and the surrounding finishes remained pristine, eliminating the need for additional repair work. The homeowner praised the swift, low‑impact execution and the transparent communication throughout the project. By delivering high‑quality general dismantling and built‑in carpentry services, we set a solid foundation for the subsequent renovation stages, demonstrating why HackingSG is the trusted partner for precise residential demolition work in Singapore.

Project Gallery

Kitchen Cabinet Hacking for Residential HDB at Choa Chu Kang - Image 1
Kitchen Cabinet Hacking for Residential HDB at Choa Chu Kang - Image 2
Kitchen Cabinet Hacking for Residential HDB at Choa Chu Kang - Image 3

More Projects

Explore our other successful projects

Ready to get started?

Work with Singapore's leading commercial and office reinstatement contractor

Contact us to discuss your project and learn how we can transform your space to suit your needs.